The Timesheet Corrections upload functionality allows financial administrators to post timesheet corrections in bulk. 


The upload functionality is available from the Financial Administration page and only users with the Financial Administration role on their account can use the functionality.


An example of a timesheet correction upload file is attached to this article.



Timesheet Correction upload rules


The following rules apply when uploading timesheet corrections.

  • The upload functionality can be used to create new timesheet correction records or update existing ones.
  • The following fields need to have a value for the timesheet correction record to be processed.
    • the date of the timesheet correction.
    • the resource external reference column to uniquely identify the resource the timesheet correction applies to.
    • the number of hours.
  • If the timesheet correction represents hours booked to a project, then the following fields are mandatory too.
    • the project external reference to uniquely identify the project the hours are booked to.
    • the project sub-activity.
  • In the case of hours booked to a miscellaneous task, then the following field is mandatory: 
    • the project that represents the name of the miscellaneous task.
  • Only records with a date that falls in open months will be processed.
  • If one or more correction records already exist for the date, resource and project combination, then all records are deleted (regardless of their sub-activity value) and replaced with the new entries. 
  • All timesheet corrections are automatically set to Approved.
  • If the file contains multiple records for the same date, resource, project and sub-activity combination, only the last record in the file is saved.




Field Description



Column Title
Description
Data Type
What happens if the field is left blank?
A. DateThe timesheet correction date.

If the date falls in a locked month, the row will be skipped.
DateThis field is mandatory. If left blank, the row will be skipped.
B. ResourceThe name of the resource the timesheet correction is for.
StringThis field is not mandatory. The upload process uses the ResourceRef value (column C) to retrieve the resource record.
C. ResourceRefThe resource username. This value is used to uniquely identify the resource record.

If no resource record can be found for this username, the row will be skipped.
StringThis field is mandatory. If left blank, the row will be skipped.
D. ProjectThe title of the project the hours are booked to or the name of the miscellaneous task the hours are booked to.

This value is only required for miscellaneous tasks.
StringThis field is only mandatory for miscellaneous tasks.

If left blank, the upload process uses the ProjectRef value (column E) to retrieve the project record.
E. ProjectRefThe project external reference value. This value is used to uniquely identify the project record.

If there is a ProjectRef value, the row will be skipped if no project record can be found for this project external reference or more than one project records exist.
StringThe row will be skipped if the Project value (column D) does not represent a miscellaneous task.
G. SubActivityThe project sub-activity the hours are booked to.

If the sub-activity is not valid for the project, the row will be skipped.
StringThis field is only mandatory for hours booked to a project. In such case, the row will be skipped if the field is left blank.
H. HoursThe number of hours (positive or negative) to be booked.NumericThis field is mandatory. If left blank, the row will be skipped.
I. NotesAny additional notes that should be recorded for this correction.StringNo note will be saved.





Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article